The Connectology® Podcast by Roadnight Taylor

Roadnight Taylor

Roadnight Taylor’s influential team of elite grid connections specialists (Connectologists®) and their expert guests help you to better understand distribution and transmission network connections, and how to acquire them faster, at less cost and at lower risk.

  1. 6d ago

    #91 Grid News and Views #20

    Data centre developers face steep new costs and tight new deadlines under Ofgem's proposed Demand Connections Reform - from six-figure commitment fees to milestones that land before financial certainty is realistic. In the latest Grid News and Views episode of the Connectology® podcast, Connectologists® Pete Aston, Rachael Eynon and Nikki Pillinger dive into what the consultation could mean, alongside lingering Gate 2 issues, the SSEP timeline and why compliance planning needs to start early. Commitment fees: Ofgem's proposed data centre commitment fee runs from £237,500.00 to £712,500.00 per megawatt, due in full on offer acceptance. The team's concern is that a fee this steep risks pushing out more than the intended speculative projects. New M0.5 milestone: a non-binding offtaker commitment is needed within six months, tough when some connection dates run to 2036. Gate 2 still shifting: some early protected' projects remain without offers, and other phase one dates are slipping into phase two due to Transmission Owner (TO) contractor resourcing and newly identified network reinforcement requirements. Compliance takes time: transmission-connected projects need at least two years' lead time, with specialist testing resource being scarce and costly. Recorded: 09 September 2026  This content was recorded on an earlier date. The connections landscape changes rapidly, so please treat any facts, figures, and guidance as a point-in-time view and verify current information before relying on it.  Our links:  Website: https://roadnighttaylor.co.uk/  Newsletter sign up: https://roadnighttaylor.co.uk/newsletter/  Follow us on LinkedIn: https://www.linkedin.com/company/roadnight-taylor-ltd/  Find if we fit at info@roadnighttaylor.co.uk

  2. Jul 14

    #89 Grid future-proofing: has standardisation gone too far?

    Connectologists® Catherine, Philip and Alex ask whether standardising substation design means we're now building too much grid.  Key themes discussed include:  the cost of going big: a substation built to serve multiple future customers can cost £100m–£150m and use up to 100 acres of land - several times the £20m–£30m it costs to build a smaller substation for a single customer  a live example: one project was moved to a new, larger substation meant to serve several customers - but most of those other customers dropped out after Connections Reform, leaving a big substation to be built for demand that no longer exists  a question of intent: is building big and scaling back later a deliberate strategy, or just a lack of one  the planning horizon: there's no Strategic Spatial Energy Plan yet to guide where new substations should go, and around fourteen years of demand is already queued up - so how far ahead should operators be planning  a risk to innovation: always reaching for a big new substation could mean that smarter options, like sharing existing bays, get overlooked  Recorded: 09 June 2026  This content was recorded on an earlier date. The connections landscape changes rapidly, so please treat any facts, figures, and guidance as a point-in-time view and verify current information before relying on it.  Our links:  Website: https://roadnighttaylor.co.uk/  Newsletter sign up: https://roadnighttaylor.co.uk/newsletter/  Follow us on LinkedIn: https://www.linkedin.com/company/roadnight-taylor-ltd/  Find if we fit at info@roadnighttaylor.co.uk

  3. Jul 7

    #88 Reform Update - Part 2: Demand Reform and Code Mods

    Pete Aston is joined by Nikki Pillinger and Alex Ikonic for a fast-moving look at Demand Reform and several Code Modifications in progress.  HV asset ownership: strong industry support for new ownership routes - either a class exemption or an Independent Transmission Owner (ITO) license. NGET is now consulting demand customers on whether they'd want to own High Voltage (HV) assets, potentially as part of some Gate 2 Phase 2 offers, with a fuller Ofgem consultation expected in autumn  CURATE pillar: Ofgem is weighing financial mechanisms and new milestones to keep only viable projects in the demand queue, with a consultation due within about a month  CMP417: would bring demand cancellation securities in line with generation; final report due to Ofgem imminently, decision expected by end of summer  CMP470: a new project commitment fee for oversubscribed technologies, rising to £25k per megawatt at maximum; consultation closed 30 June  CMP460/DCP461: deciding how Super Grid Transformer costs are charged — a second industry vote produced no clear consensus, so the decision now sits with Ofgem  Recorded: 25 June 2026  This content was recorded on an earlier date. The connections landscape changes rapidly, so please treat any facts, figures, and guidance as a point-in-time view and verify current information before relying on it.  Our links:  Website: https://roadnighttaylor.co.uk/  Newsletter sign up: https://roadnighttaylor.co.uk/newsletter/  Follow us on LinkedIn: https://www.linkedin.com/company/roadnight-taylor-ltd/  Find if we fit at info@roadnighttaylor.co.uk

  4. Jul 1

    #87 Reform Update - Part 1: Gate 2 Offers

    Developers and investors have spent the past year navigating Gate 2 applications, hoping for offers that would clearly de-risk their projects. In this episode, Connectologist® Pete Aston is joined by Connectologists® Nikki Pillinger and Rachael Eynon to unpack what is actually showing up in those offers and the queue changes ahead.  Offer progress: transmission and distribution protected offers have now been issued, with around 400 accepted and only seven declined so far  Unhelpful clauses: some protected offers include caveats suggesting transmission costs or assessments could still change, which Nikki Pillinger flags as inconsistent with the methodology for protected projects  Cost increases: several DNOs are showing significant cost rises beyond the expected 30 to 40%, with some linked to new delivery frameworks  Industry workshop outcomes: requests for earlier sight of transmission works, more flexible acceptance windows for staged connections, and better prioritisation of post-offer queries  New working groups: CIDEF (Connections Investor/Developer Engagement Forum), led by Ofgem, and a separate DNO consistency group from RenewableUK  Methodology updates: queue protections will remain for all projects, not just batteries, alongside new prioritisation for hybrid and repowering projects  Mod App scoping: NESO is gathering early views on project changes ahead of the next Gate 2 window, with a tight 10 July deadline  Recorded: 25 June 2026  This content was recorded on an earlier date. The connections landscape changes rapidly, so please treat any facts, figures, and guidance as a point-in-time view and verify current information before relying on it. Our links:  Website: https://roadnighttaylor.co.uk/  Newsletter sign up: https://roadnighttaylor.co.uk/newsletter/  Follow us on LinkedIn: https://www.linkedin.com/company/roadnight-taylor-ltd/  Find if we fit at info@roadnighttaylor.co.uk

  5. May 18

    #86 Grid News and Views #19

    Connectologists® Pete Aston, Philip Bale, and Alex Ikonic return for another GNV session, covering the developments shaping the connections landscape right now. The episode explores: Gate 2 offer progress is moving steadily, with 100% of protected transmission offers issued and distribution at 39%, though Phase 1 offers (to 2030) arriving mid-May to September are expected to bring more complex terms and cost increases. Technical queries are critical as some offers have contained material errors, developers are urged to raise queries within the four-week window before accepting. Demand connections reform is gaining momentum, with an estimated 50+ gigawatts of data centre capacity in the queue and consultations underway on viability measures, alongside demand registers expected later this year. ANM curtailment risk is proving greater than forecast for many connected projects, with unclear LIFO positions, data errors, and Gate 2 queue restructuring all adding uncertainty. Transmission delays are already reaching customers, with no equivalent financial consequence for transmission owners - an asymmetry the Connectologists® flag as requiring urgent attention. Recorded: 12 May 2026 This content was recorded on an earlier date. The connections landscape changes rapidly, so please treat any facts, figures, and guidance as a point-in-time view and verify current information before relying on it.   Our links: Website: https://roadnighttaylor.co.uk/ Newsletter sign up: https://roadnighttaylor.co.uk/newsletter/ Follow us on LinkedIn: https://www.linkedin.com/company/roadnight-taylor-ltd/ Find if we fit at info@roadnighttaylor.co.uk

  6. Apr 20

    #85 Hypercube's AI perspective with Adam Sroka, CEO, Hypercube

    Rachael Eynon is joined by Adam Sroka, CEO of Hypercube, a specialist data and AI consultancy focused on the energy sector, to explore how energy organisations can navigate AI adoption safely and practically. Adam explores: How the energy sector is roughly a decade behind leading tech industries in AI adoption — caution that exists for good reason given the complexity of multi-stakeholder energy systems His "risk staircase" approach favours the lowest-risk use case that proves value and builds confidence before scaling up AI as a quality check: using one model to critique or score the output of another is a practical pattern that could help organisations improve the reliability of AI-generated work without heavy overhead AI's role in Connections Reform: as grid connection processes grow more complex, there may be opportunities for AI to improve data accessibility, transparency, and decision-making across the connections landscape Connectologist® Catherine Cleary also joined Adam on the Hypercube Energy Podcast, exploring grid connection reform, queue management, and the future of connections from an engineer's perspective — you can listen to that conversation here: https://wearehypercube.com/grid-reform-queue-management-and-the-future-of-connections/ Recorded: 30 March 2026 This content was recorded on an earlier date. The connections landscape changes rapidly, so please treat any facts, figures, and guidance as a point-in-time view and verify current information before relying on it.   Our links: Website: https://roadnighttaylor.co.uk/ Newsletter sign up: https://roadnighttaylor.co.uk/newsletter/ Follow us on LinkedIn: https://www.linkedin.com/company/roadnight-taylor-ltd/ Find if we fit at info@roadnighttaylor.co.uk

  7. Apr 13

    #84 Grid News and Views #18 - Part 2

    Kyle Murchie, Nikki Pillinger, and Rachael Eynon return for Part 2 of GNV18, covering Ofgem's end-to-end review progress and the rapidly evolving demand connections landscape.  Ofgem's end-to-end review: working groups are already delivering, with DNOs and NESO committed to publishing registers of accepted demand connections from one megawatt and above  Guaranteed connection dates: Nikki notes DNOs are open to the concept but timing must link to meaningful developer milestones — financial investment decision, contractor appointment, or construction planning — not offer stage  Data transparency: SSEN and UKPN have improved demand data tools, now separating BESS and non-BESS demand at substation level  Demand queue growth: the combined transmission and distribution queue grew from approximately 42 gigawatts to around 125 gigawatts between summer 2024 and summer 2025, driven by AI data centres, hydrogen, and industrial decarbonisation  Information Request Notice: a mandatory NESO request targeting Gate 1 and Gate 2 demand customers requiring detailed project progress and financial information — closed on the 13 April 2026, with concerns raised about response quality given tight timescales  DESNZ strategic demand consultation: running in parallel with responses due 15 April 2026, exploring enhanced queue readiness requirements, a strategic demand project designation process, and potential regional targets for data centre placement  Recorded: 07 April 2026  This content was recorded on an earlier date. The connections landscape changes rapidly, so please treat any facts, figures, and guidance as a point-in-time view and verify current information before relying on it.   Our links:   Website: https://roadnighttaylor.co.uk/   Newsletter sign up: https://roadnighttaylor.co.uk/newsletter/   Follow us on LinkedIn: https://www.linkedin.com/company/roadnight-taylor-ltd/   Find if we fit at info@roadnighttaylor.co.uk

About

Roadnight Taylor’s influential team of elite grid connections specialists (Connectologists®) and their expert guests help you to better understand distribution and transmission network connections, and how to acquire them faster, at less cost and at lower risk.

You Might Also Like